New White Park Playground price rises, fundraising underway
Published: 04-13-2025 10:01 AM |
A long-awaited new playground at White Park will cost $60,000 more than expected, and residents are aiming to raise that amount in the next month.
With ramps, solid surfacing, and a wheelchair-accessible swing and merry-go-round, the playground will be the first in the region that is fully accessible.
City leaders approved the project in January 2024 and construction was expected to start last fall. The delay and construction inflation combined to tack on the additional price. The aggressive 30-day fundraising deadline was set so that construction can happen in the coming months, according to Jonathan Smith, chair of the Friends of White Park.
City Manager Tom Aspell said the city is not planning to put further public dollars toward the new cost.
The project’s $800,000 price tag approved last year was covered by $350,000 of city money, $50,000 in community donations, and a $400,000 land and water conservation grant.
Smith said he is optimistic that the new fundraising goal will be met.
The current Monkey Around Playground at White Park was built in 1994 with donations and community labor and is more than a decade past its expected 20-year lifespan.